Construction schedule for Maho Bay LLC project in St. John, USVI, including timeline and completion details.

👤 Named in This Document
No named persons linked yet

📋 Key Excerpts6

PersonKeyword
Excerpt 1
MAHO BAY USVI, LLC: Construction Schedule ST JOHN, USVI ID Task Name Duration Start Finish % Complete 1 Pool Shade Structure & Engineering Doors 45 days
Excerpt 2
, LLC: Construction Schedule ST JOHN, USVI ID Task Name Duration Start Finish % Complete 17 (8) Poured in place 16" square concrete columns 4 days Tue
Excerpt 3
, LLC: Construction Schedule ST JOHN, USVI ID Task Name Duration Start Finish % Complete 29 Substantial completion date 1 day Thu 8/8/19 Thu 8/8/19 0%

Discussion

Let the world know how you feel.

What you just read should make you angry. Channel that into 17 syllables. Our AI helps you craft a haiku in seconds — then share it with the world.

Power hides in dark But sunlight finds every crack Truth cannot be bought

— Sarah K., after reading this document
✍️ Write Your Haiku

Haikus for Humanity — 5 · 7 · 5

React
Share𝕏🦋FBinFund Accountability